New Ad 1

New 1

الخميس، 24 نوفمبر 2016

The Most Important Equations in Cost Management in PMP & in PMI-ACP Exams




Cost Variance (CV)
CV = EV – AC
EV = Earned Value
AC = Actual Cost
< 0    Over budget
= 0    On budget
> 0    Within budget



Schedule Variance (SV)
SV = EV – PV
EV = Earned Value
PV = Planned Value
< 0    Behind schedule
= 0    On schedule
> 0    Ahead of schedule
Cost Performance Index (CPI)
CPI = EV/AC
EV = Earned Value
AC = Actual Cost
< 1    Over budget
= 1    On budget
> 1    Under budget

sometimes the term ‘cumulative CPI’ would be shown, which actually is the CPI up to that moment






Schedule Performance Index (SPI)
SPI = EV/PV
EV = Earned Value
PV = Planned Value
< 1    behind schedule
= 1    on schedule
> 1    ahead of schedule
Estimate at Completion (EAC) if original is flawed
EAC = AC + New ETC
AC = Actual Cost
New
ETC = New Estimate to Completion
if the original estimate is based on wrong data/assumptions or circumstances have changed
Estimate at Completion (EAC) if BAC remains the same
EAC = AC + BAC – EV
AC = Actual Cost
BAC = Budget at completion
EV = Earned Value
the variance is caused by a one-time event and is not likely to happen again
Estimate at Completion (EAC) if CPI remains the same
EAC = BAC/CPI
BAC = Budget at completion
CPI = Cost performance index
if the CPI would remain the same till end of project, i.e. the original estimation is not accurate
Estimate at Completion (EAC) if substandard performance continues
EAC = AC + [(BAC -EV)/(CPI*SPI)]
AC = Actual Cost
BAC = Budget at completion
EV = Earned Value
CPI = Cost Performance Index
SPI = Schedule Performance Index
use when the question gives all the values (AC, BAC, EV, CPI and SPI), otherwise, this formula is not likely to be used
To-Complete Performance Index (TCPI)
TCPI = (BAC –EV)/
(BAC – AC)
BAC = Budget at completion
EV = Earned value
AC = Actual Cost
TCPI = Remaining Work
/Remaining Funds
BAC = Budget at completion
EV = Earned value
CPI = Cost performance index
< 1    Under budget
= 1    On budget
> 1    Over budget
Estimate to Completion 
ETC = EAC -AC
EAC = Estimate at Completion
AC = Actual Cost
Variance at Completion
VAC = BAC – EAC
BAC = Budget at completion
EAC = Estimate at Completion
< 0    Over budget
= 0    On budget
> 0    Under budget
PERT Estimation (3 Points Estimate)
(O + 4M + P)/6
O= Optimistic estimate
M= Most Likely estimate
P= Pessimistic estimate
Standard Deviation
(P – O)/6
O= Optimistic estimate
P= Pessimistic estimate
this is a rough estimate for the standard deviation
Float/Slack
LS – ES
LS = Late start
ES = Early start
LF – EF
LF = Late finish
EF = Early finish
= 0    On critical path
< 0    Behind schedule


Communication Channels
n (n-1)/2
n = number of members in the team
n should include the project manager

e.g. if the no. of team members increase from 4 to 5, the increase in communication channels:
5(5-1)/2 – 4(4-1)/2 = 4


One Point Estimate
(O + M + P)/3
O= Optimistic estimate
M= Most Likely estimate
P= Pessimistic estimate


الاثنين، 21 نوفمبر 2016

Free PMP Online Training Course

Free PMP Online Training Courses by VMedu

VMedu is an educational institute offers free PMP online course, Attendance certification of PMP will be granted upon completion of the course, and it will let you eligible for scheduling PMP exam



Check the links below

http://demo.vmedu.com/Courses/CourseOverview

الثلاثاء، 15 نوفمبر 2016

Most Repetitive Questions in PMP Exam- Guarantee up to 36 marks out of 200 if you got these points

PMP Repetitive and Usual Questions- Guarantee up to 36 marks out of 200 if you got 
these points




PMI is using a bank questions for their exams, it is impossible to find the same description for a question in a PMI exam to be repeated in another exam, but the same idea, meaning and point of view is usually repeated, if you understand and considered the below points you will got up to 30 correct point in your exam.


1.   Delphi technique; the experts judgment- Always there is a direct question on it (1 Point)

2.   Characteristics of the project, has a start and end, and specific goals- always there is 1 direct question on the project characteristics (1 Point)

3.   Input, Tools & Techniques, Output,, there are about 7-10 questions asking to extract which one of the choices is or isn’t an input, output, T&T (9 Points)

4.   Expected Monetary Value (EMV) and Communication channels n*(n-1)/2, there is usually 2 questions about them in the exam (2 Points)

5.    Cost analysis equations EV, SPI, CPI, TCPI… etc. and usually you 
will face an average of 4 questions about this topic (4 Points)

 visit the link below to know all of the equations & formulas that is main to 
memorize before registering to PMP exam

http://academyoflions.blogspot.com/2018/07/main-formulas-you-have-to-memorize-to.html


6.   Differences between Cost plus, fixed price, T&M contracts and come as questions asking you to select the right or the wrong choice about the major differences between the contract types (3 Points)

7.    Code of ethics and professional behavior, and usually you will find 1 direct question about this topic regarding the manners and behavior of the project manager but you will see many choices in other questions show these behaviors (1 Point)

8.   Project Scope Statement, Scope of Work, WBS, WBS dictionary and project constraints, two direct questions about them can be detected in your exam (2 Points)
9.   The network diagram, calculating durations of activities, Early and late start, Early and late finish, Slag, critical and near critical path, crash and most risky activities, all of these topics will be covered in the exam 
(7 Points)
10. Monte Carlo Simulation which is usually 2 direct questions on it

see the link below for more information about Monte Carlo Simulation in PMP Exam


http://academyoflions.blogspot.com/2016/09/monte-carlo-simulation.html

11. which Process comes next?? just remember that Planning phase processes are coming as per their order, for the other processes such as Initiating , Monitoring & controlling, execution & closing, their processes are not necessary to be in order, just the planning processes  
&
you have to memorize them for the exam.
5 Points 


12. Tornado diagram, usually and at least there is 1 direct question about  it (1 Point)


Note that the most important factor during the PMP exam is the time, controlling the time and solving the questions based on strategic plan for you will let you finish on the right way.


K4

Most Repeated Topics in Reading Section in TOEFL Exams

Reading Section is one important part in both IELTS & TOEFL Exams which constitute 25% of the overall score in exam. After studying Hun...

text ad

Sidebar

lacademy